PowerNews publishes the financial proposals of the competing companies at the West Port Said Transformer Station, Effort 66/6/20, where the lowest priced Swedish bid came after opening the business envelope today, and the T&D Subdivision offer reached approximately 329.6 million pounds, while the Madkour Engineering Projects offer amounted to 347.2 million EGP
The following are the company’s rates according to the Power News website:
1- El-Sewedy Electric Company “T&D” amounted to 329,637,450.30 EGP.
2- Madkour Company for Engineering Projects 347.169181.16 EGP.
3- Giza Textile Systems with HYOSUNG alliance 387,989,940.53 EGP.
4- Alliance NCC and Mega Construction 503.423.260.40 EGP.
5- Energia Company 513,715,764.48 EGP.