Adel El Banhsawy.
The Alliance of Giza Misr For Transmissions and Distribution and the Arab Egyptian Co. for Electrical Industries, Zaki El-Sewedy, placed first in the lowest priced tender line connecting Housh Eissa, with a voltage of 66 kV and a length of 20 km (2×10 km). Each alliance is in detail, so you can arrange your offers so prices.
Their offer won the first place as the least offered price in which it was EGP 62,526,658 before the discount and reached EGP 59,400,325 after 5% discount.
On second, High Dam Electrical and Industrial Projects Alliance with Wadi El Nile came with an offer of EGP 65,269 443.
Followed by Mega for Constructions and Industries’ EGP 68,329,798 offer.
Finally, Kahromika Company’s offer was about EGP 68,945,006 after 8% discount.
GMT&D haslong past experience in building the linkag lines for different transmissions, in addition to the working transformers in the network.
Currently, the company is implementing a 500kV Zagazig Transformer Station aligning with Power China and West El Sherouk Transformer Startion. Not only that but also, it executed the biggest part in the linkage line between Egypt and Sudan.