The NMP unit will be operated in mid-February or may exceed this period, claimed by an official source at Alexandria petroleum company.
He clarified that there are certain procedures and steps should be completed before the operation; such as the repair of 3 feed pumps of unit 2000, for which the RuhrPumpen global repairs the mechanical wires; also, the wrapping of the nitrogen compress for unit 4000 after an emission in the insulation motor; which was sent to be repaired by the Siemens agent and the remaining gaskets for unit 3000.
The official pointed out that, in addition to all of that, the procedures of the assignment order are being finalized to import 300 tons of NMP after consuming 380 tons used in the operation experiments.